冷再生機施工中如何處理接縫問題
來源:http://www.stkehao.cn/ 日期:2023-07-10
路面的接縫問題就是冷再生機在對道路進行施工中停機所導致的,每次停機,哪怕只是停機幾分鐘用于更換罐車,也會造成路面再生材料鋪設的橫縫,縫隙的產生會影響到接下來再次施工時的材料的均勻性。因此在施工的過程中應當盡量避免停機,事不可為的話,應當及時的對縫隙進行處理。下面冷再生機租賃廠家就來講解一下如何處理接縫問題。
The joint problem on the road surface is caused by the shutdown of the road during the construction of the cold reinvigoration process. Even if the shutdown is only for a few minutes to replace the tank truck, it can cause transverse joints in the laying of recycled materials on the road surface. The generation of cracks will affect the uniformity of the materials during the subsequent construction. Therefore, during the construction process, it is necessary to avoid downtime as much as possible. If things cannot be done, the gaps should be dealt with in a timely manner. Below, the cold regeneration machine rental manufacturer will explain how to handle the seam problem.
1、在臨時停機后重新開始施工時,整個再生機組應倒退1.5~2m的距離到達再生過的材料上,以保證開始施工后所有材料均得到處理。
1. When resuming construction after a temporary shutdown, the entire regeneration unit should be backed up by a distance of 1.5-2m to reach the recycled material, to ensure that all materials are processed after starting construction.
2、上一作業段壓實時,要預留4~6m不進行碾壓,待下一段碾壓時一并壓實。
2. During the compaction of the previous operation section, a distance of 4-6 meters should be reserved for no compaction, and the next section should be compacted together.
冷再生機租賃
3、由于再生機開始工作時要使轉子全部下切到再生層的底部來打碎再生料,前進速度為0,使得翻松的再生料混合不均勻,為此,需人工進行翻拌后將坑槽找平。
3. Due to the fact that when the regeneration machine starts working, it needs to cut all the rotors down to the bottom of the regeneration layer to break the recycled material, with a forward speed of 0, resulting in uneven mixing of the loosened recycled material. Therefore, it is necessary to manually mix and level the pit.
再生機的工作寬度一般要小于再生路面的寬度。因此,全幅路的再生需要多次作業,從而導致數條相鄰作業面間的縱向接縫。
The working width of the recycling machine is generally smaller than the width of the recycled road surface. Therefore, the regeneration of the full width road requires multiple operations, resulting in longitudinal joints between several adjacent working surfaces.
一般來講,相鄰作業面間的小重疊量為10cm,以保證縱縫處再生料的連續性,同時避免相鄰作業面間存在未再生的夾帶。
Generally speaking, the small overlap between adjacent working surfaces is 10cm to ensure the continuity of recycled material at the longitudinal joint, while avoiding the presence of unrecycled entrainment between adjacent working surfaces.
冷再生機施工中如何處理接縫問題相關事項就講解完畢了,希望能夠給您好的幫助,更多事項就來我們網站http://www.stkehao.cn進行咨詢!
We have finished explaining the relevant matters on how to handle the joint problem during the construction of the cold recycling machine. We hope to provide you with good help. For more information, please come to our website http://www.stkehao.cn Consulting!