公司新聞
道路基層冷再生施工要注意什么?
來源:http://www.stkehao.cn/ 日期:2023-02-13
1.1材料準備
1.1 Material preparation
在實際的道路基層冷再生施工作業過程中,主要用到的施工材料有瀝青面層銑刨料、水泥和水等等。通常大部分施工單位在選擇水泥時,由于考慮到水泥化熱問題,所以一般都會采用硅酸鹽水泥,或是礦渣硅酸鹽水泥等,這是因為此類水泥含有的水泥化熱量較少,能夠防止施工裂縫的出現。
In the actual process of cold recycling construction of road base, the main construction materials used are asphalt surface milling material, cement and water, etc. Generally, most construction units will use Portland cement or slag Portland cement due to the consideration of the heat of cementation when selecting cement. This is because such cement contains less heat of cementation and can prevent the occurrence of construction cracks.
并且,施工單位還要對新入廠的水泥質量進行嚴格的控制,堅決不允許使用變質的水泥。其次,施工單位還需要確保水泥強度真正達到了國家規定標準要求,無論是水泥齡期,還是穩定性,都滿足了工程施工要求。而一般水泥初凝時間都在3-5小時左右,最后的終凝時間大概在6小時。
In addition, the construction unit should also strictly control the quality of new cement entering the factory, and never allow the use of deteriorated cement. Secondly, the construction unit also needs to ensure that the cement strength truly meets the requirements of the national standards, whether the cement age or stability, meet the requirements of the project construction. Generally, the initial setting time of cement is about 3-5 hours, and the final setting time is about 6 hours.
另外,道路基層冷再生施工工藝對于用水方面有著較高的要求,施工單位應該盡量采用飲用水,或是完全沒有毒害物質的純凈水。再者,在對銑刨料選用時,也要確保料粒直徑規格的一致,必須切實結合工程施工需要,選擇出合適理想的銑刨料。最后,碎石作為基層混合料中主要的構成材料,應當對其強度、壓碎值等當面進行規范要求。
In addition, the road base cold regeneration construction process has high requirements for water use. The construction unit should try to use drinking water or pure water without toxic substances. In addition, when selecting milling materials, it is also necessary to ensure the consistency of grain diameter and specification. It is necessary to select suitable and ideal milling materials according to the needs of engineering construction. Finally, as the main constituent material of the base course mixture, the strength and crushing value of the crushed stone should be standardized.
1.2冷再生混合料配合比設計
1.2 Mix design of cold recycled mixture
在道路基層冷再生混合料配合比設計中主要包括3個方面,如原材料分析、配合比設計及設計配合比檢驗。遵循《公路工程路而基層施工技術規范》進行混合料配合比的準確設計,確保施工質量。
The mix design of cold recycled mixture for road base mainly includes three aspects, such as raw material analysis, mix design and design mix inspection. Follow the Technical Specifications for Construction of Road and Base Course of Highway Engineering to accurately design the mixture ratio and ensure the construction quality.
冷再生施工現場
Cold regeneration construction site
2道路基層冷再生施工工藝的應用
2. Application of cold regeneration construction technology for road base
現如今,伴隨著國民經濟與科學技術的高速發展,我國城市化建設規模也在不斷的擴大與完善,尤其是面臨當前市場競爭如此激烈的形勢,人們對于公路工程質量要求也提出了更高層次的要求,而在實際的公路工程施工過程中,每一個施工階段之間都有著緊密相連的關系,一旦其中任何一個施工環節出現失誤,都將會對整個工程施工質量造成不同程度的影響,甚至還會產生巨大的經濟損失。
Now, with the rapid development of national economy and science and technology, the scale of urbanization construction in China is also expanding and improving. Especially in the face of the current situation of fierce market competition, people have also put forward higher requirements for the quality of highway engineering. In the actual process of highway engineering construction, each construction stage has a close relationship, Once any of the construction links make mistakes, it will affect the construction quality of the whole project to varying degrees, and even cause huge economic losses.
而冷再生施工技術作為現代公路工程建設中常用的技術手段之一,其施工質量的好壞將會對公路整體安全穩定性有著直接的影響,為了避免危險隱患的發生,無論是當地管理部門,還是施工企業,都必須加強做好施工現場質量控制工作,全面掌握當地地質條件、自然環境情況,制定出規范的施工流程和施工工序,采用先進的施工技術和施工工藝,從根本上確保公路工程的施工質量。
As one of the commonly used technical means in the construction of modern highway engineering, the construction quality of cold regeneration construction technology will have a direct impact on the overall safety and stability of the highway. In order to avoid the occurrence of hidden dangers, both local management departments and construction enterprises must strengthen the quality control of the construction site and comprehensively grasp the local geological conditions and natural environment, Formulate standardized construction process and construction procedure, adopt advanced construction technology and construction process, and fundamentally ensure the construction quality of highway engineering.
2.1施工放樣
2.1 Construction setting out
按照原有路基銑刨過的標高和冷再生混合料底新鋪基層的設計標高及經試驗段確定的松鋪系數,將新鋪底基層的攤鋪高程計算出來,并進行施工放樣作業。
According to the milled elevation of the original subgrade, the design elevation of the newly paved base course of the cold recycled mixture and the loose paving coefficient determined by the test section, the paving elevation of the newly paved base course is calculated and the construction lofting operation is carried out.
2.2路面平整
2.2 Pavement leveling
將原有路面存有的雜物清理干凈,將邊線也清理干凈,同時將再生路段上面的井蓋等結構物清除,將原有路面進行翻漿、車轍、沉陷等病害處理作業,確保原有路面的平整性。
Clean up the sundries on the original road surface, clean up the sidelines, and remove the manhole covers and other structures on the regenerated road surface, and carry out the treatment of diseases such as frost boiling, rutting and subsidence on the original road surface to ensure the smoothness of the original road surface.
2.3準備新加料
2.3 Prepare for new feeding
在每平米新料添加量的計算中必須嚴格遵循原有路內再生深度的平均密度進行計算。按照每車料的多少進行其堆放距離的確定。在對每平方米穩定層水泥用量計算時,必須嚴格遵循水泥劑量要求進行,并對水泥擺放的縱橫間距進行確定。
The calculation of the amount of new material added per square meter must strictly follow the average density of the regeneration depth in the original road. The stacking distance shall be determined according to the amount of materials in each vehicle. When calculating the cement dosage per square meter of stabilized layer, the cement dosage requirements must be strictly followed, and the vertical and horizontal spacing of cement placement must be determined.
2.4冷再生拌和
2.4 Cold regeneration mixing
在原有路面上水車在冷再生機租賃的推動下前行,遵循原有路面損壞情況及再生深度對行駛速度進行適當地調整及控制,通常都會將速度控制在每分鐘6到12米,確保銑刨后料的級配不會產生較大的波動,在網裂較為嚴重的路段,必須將再生機組的行駛速度進行有效降低,并將銑刨轉子的轉速進行適量地提升。在再生機行駛中必須有工作人員跟隨在其后面,以便對再生深度進行隨時檢查,同時還要對水泥含量及混合料的含水量進行檢測,調整時,要與再生機工作人員相配合。
The waterwheel on the original road is driven by the cold recycling machine lease, and the driving speed is properly adjusted and controlled according to the original road damage and the regeneration depth. Usually, the speed is controlled at 6 to 12 meters per minute to ensure that the grading of the milled material will not have a large fluctuation. In the road section with serious mesh cracks, the driving speed of the recycling machine must be effectively reduced, Increase the speed of the milling rotor appropriately. During the operation of the regenerator, there must be staff following it to check the depth of regeneration at any time. At the same time, the cement content and the water content of the mixture should be detected. When adjusting, the staff of the regenerator should be coordinated.
2.5碾壓整形
2.5 Rolling and shaping
再生機施工后初壓時,應選用鋼輪振動壓路機,壓實過程中要選用高幅低頻壓實,壓實遍數必須符合再生層底部2/3厚度范圍內的壓實度。鋼輪壓路機行駛速度必須控制在每小時3千米以下。在完成初壓后,整形施工可以選用平地機進行。
During the initial compaction after the construction of the regeneration machine, the steel wheel vibratory roller shall be selected. During the compaction process, the high amplitude and low frequency compaction shall be selected. The number of compaction times must meet the compaction degree within the range of 2/3 thickness of the bottom of the regeneration layer. The traveling speed of steel wheel roller must be controlled below 3 kilometers per hour. After the initial compaction, the shaping construction can be carried out with grader.
按照從兩側向中間的順序平地機在直線路段上進行施工,特殊情況下,還要在進行一次刮平作業。按照從中間到兩側的順序平地機在曲線路段進行刮平作業。碾壓施工中遵循先邊部后中間、由輕到重、由慢到快的順序進行,特別是超高路段必須遵循從中間到兩邊的順序進行碾壓施工。
The grader shall carry out the construction on the straight road section in the sequence from both sides to the middle. In special cases, a leveling operation shall also be carried out. The grader shall carry out leveling operation on the curve section in the sequence from the middle to both sides. The rolling construction shall follow the sequence of starting from the edge to the middle, from light to heavy, and from slow to fast, especially for the superelevation section, the rolling construction must follow the sequence of starting from the middle to both sides.
2.6接縫與調頭處理
2.6 Joint and turning treatment
施工人員在對縱向接縫進行處理的過程中,應該對道路寬度進行合理的設置,若是發生縱向重疊的情況,就要采取全幅施工方法,盡最大限度的將重疊量降到最低,同時也可以進一步提高施工效率。并且,施工單位還要對全幅施工與半幅施工的時間差進行有效的控制,不能太久,也不可以太短,需要按照工程施工需求,適當的加大重疊量。另外,在對橫向調頭進行處理時,應事先對產生的橫向接縫進行處理,以免出現停機現象。
During the treatment of longitudinal joints, the construction personnel should reasonably set the width of the road. In case of longitudinal overlap, the full-width construction method should be adopted to minimize the overlap as much as possible, and at the same time, the construction efficiency can be further improved. In addition, the construction unit also needs to effectively control the time difference between full-width construction and half-width construction, which cannot be too long or too short. It is necessary to appropriately increase the amount of overlap according to the construction needs of the project. In addition, when dealing with the transverse turning, the transverse joints should be treated in advance to avoid the shutdown phenomenon.
本文由冷再生機租賃整理發布,您是不是對這些內容有所了解了呢?更多的內容請點擊:http://www.stkehao.cn我們會有更多精彩內容等你查看。
This article is released by the Cold Recycling Machine Leasing and Sorting Department. Do you know something about these contents? For more information, please click: http://www.stkehao.cn We will have more wonderful content waiting for you to check.